Opened, Stopped and Unplugged Machine

OPENED, STOPPED AND UNPLUGGED MACHINE

  • Measure partial discharge off-line

  • Measure insulation resistance i.r
    according to UQ602011C standard

  • Determine polarization index i.p.
    according to ieee std 43-2000 standard

  • Measure tangent of loss angle tan δ in winding insulation and its variation in δ tan δ
    based on voltage: 0.2 – 0.4 – 0.6 – 0.8 –rated voltage

  • Measure μf winding of electrical windings respect to the mass, compared with same voltage
    present in the previous point test ground voltage
    according to UQ602010C standard

  • Test balance of phases through ohmic resistance
    according to UQ602012C standard

  • Test balance of phases through impedance z ohm
    according to ieee std 56-1977 standard

  • Check up motor space heaters and thermoelements

  • Check status of closures

  • Check status of keys
    according to UQ602028C standard

  • Check status of anti-effluvium protection

 

ROTOR OUT OF STATOR

  • Measure insulation resistance i.r
    according to UQ602011C standard

  • Check total static ohmic resistance and in every single pole
    according to UQ602012C standard

  • Check total static impedance z ohm and in every single pole
    according to ieee std 56-1977 standard

 